OpenLedger
The client wants more flexibility while the team wants sign-off. Do you change the delivery model now?
Decision owner:CEO / delivery owner
Complete operation film
What you are being asked to decideThe visible dispute was milestone acceptance versus a time-boxed sprint.
Cost of getting it wrongYou may change process without fixing who can accept work—so revisions and conflict continue.
Marcus · DecisionThe visible choice between milestones and sprints is premature.
Evelyn · Evidence & riskThe thread contains requests, but no shared acceptance rule or named approver.
Sofia · Stakeholder impactChanging process without authority merely moves the conflict into the next cycle.
Minerva Team's provisional judgmentBoth options fail until someone has final acceptance authority and a shared definition of done.Name the final accepter and one testable stage outcome before the pilot.
The question only you can resolveWho has final authority to say this stage is done?
Watch the complete operation film →
See why the Minerva Team reached this judgment
Analysis work receipt
1official source7model calls10/10decision checks131.5actual runtime